In July 2021, the Department of Planning, Industry and Environment approved the project’s Independent Environmental Audit (IEA).

In June 2021, the Department of Planning, Industry and Environment approved an Out of Hours Work (OOHW) protocol. This is to allow a previous extension to working hours at project site due to COVID.

Key achievements;
Piling, Tracker, and Module installation are all completed.
132kv Substation is completed and connected to the network.
Solar Farm has completed R1 Registration within the NEM. R2 Testing is in progress.